Article Image

Stratford Leisure Centre

Mace Group Ltd

Refurbishment and extension to existing building whilst centre was operational. Amongst the product supplied was pool side doorsets and changing areas.

Project title:                              Stratford Leisure Centre
Client:                                       Stratford District Council
Architect:                                  Weedon Architects
PQS:                                          Mace Group
Sub-contractor:                       Speller Metcalfe Ltd
Main contractor:                          -

Qty of doors:                              69
Qty of frames:                            49
Qty of overpanels:                     0
Qty of screens:                           0 

Fire ratings:                                NFR and FD30s
Acoustic rating:                          None 

Frame profile:                             SPL (Solid plain lining) and CFP (“Cleanform Plain”)
Frame material/finish:                  St-Beech/Primed and St-Beech/Wrapped
Architrave:                                  AR1 (44mm x 14mm) and PFAR2 (48mm x 18mm)
Architrave material/finish  :           Poplar/primed and St-Beech/Wrapped

Door Facing:                                Formica laminate (Mouse F7928 MAT) and Postformed Acrovyn (162 Charcoal)
Finish:                                        -
Lip Material/Finish:                      Maple/polished
Vision panel arrangement:            1SLN (top: 1450mm (H) x 200mm (W)
Glazing bead profile:                    Bolection and “Flushform”
Glass:                                           Clear    

Ironmongery:                              Supply and fit 316 grade hinges throughout. Recess only customer samples

Key details:                                 Flat laminate and WR Postformed

Project value:                              £4.5m              

Approx. Lead-time:                      From receipt of order 3 weeks for flat laminate and 5 weeks for Postform

Principal Doorsets came to site to support us in specification, dimensioning and program. They were most helpful and provided information and support throughout the on site phase of the project